File #: 210374    Version: 1 Name:
Type: Ordinance Status: Agenda Ready
File created: 4/30/2021 In control: Council
On agenda: 5/6/2021 Final action:
Title: Authorizing an $8,829,618.38 construction contract with Enerfab Power & Industrial, Inc., for the Secondary Switchgear Improvements at the Water Treatment Plant project; authorizing a maximum expenditure of $9,712,618.38; and authorizing a $1,140,766.00 Design Professional Services Amendment No. 1 for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant for Contract No. 9489 with HDR Engineering, Inc., for a total contract amount of $2,571,616.00.
Attachments: 1. 210374 Fact Sheet, 2. 210374 Fiscal Note, 3. 210374 Docket Memo, 4. 210374Approved DPS RFM

ORDINANCE NO. 210374

 

 

title

 

 Authorizing an $8,829,618.38 construction contract with Enerfab Power & Industrial, Inc., for the Secondary Switchgear Improvements at the Water Treatment Plant project; authorizing a maximum expenditure of $9,712,618.38; and authorizing a $1,140,766.00 Design Professional Services Amendment No. 1 for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant for Contract No. 9489 with HDR Engineering, Inc., for a total contract amount of $2,571,616.00.

 

body

 

 BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section 1. That the Director of the Water Services Department is authorized to execute Contract No. 9569 in the amount of $8,829,618.38 with Enerfab Power & Industrial, Inc., for the Secondary Switchgear Improvements at the Water Treatment Plant project, Project No. 80002134. A copy of the contract is on file in the office of Water Services.

Section 2. That the Director of the Water Services Department is authorized a maximum expenditure of $9,712,618.38 from Account No. AL-8077-807773-611060- 80002134, Water Treatment, to satisfy the cost of this contract.

Section 3. That the Director of the Water Services Department is authorized to execute a Design Professional Services Amendment No. 1 to Contract No. 9489 in the amount of $1,140,766.00, for a total contract amount of $2,571,616.00 with HDR Engineering, Inc., for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant project, Project No. 80002134. A copy of the amendment is on file in the office of Water Services.

Section 4. That the Director of the Water Services Department is authorized a maximum expenditure of $1,140,766.00 from Account No. AL-8077-807773-611040- 80002134, Water Treatment, to satisfy the cost of this amendment.

_____________________________________________

I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.

end

______________________________________________________

 

                                                                                                _____________________________

                                                                                                Tammy L. Queen

                                                                             Director of Finance

 

Approved as to form and legality:

 

______________________________

Mark P. Jones

Assistant City Attorney