File #: 250296    Version: 1 Name:
Type: Ordinance Status: Referred
File created: 3/3/2025 In control: Transportation, Infrastructure and Operations Committee
On agenda: 4/22/2025 Final action:
Title: Sponsor: Director of Public Works Department Authorizing the Director of Public Works to execute a design-build contract with Gunter Construction Company in the amount of $2,887,595.00 for the 31st St Connector Plan Phase 1 Sidewalks project, from Main Street to Gillham Plaza; authorizing the Director of Public Works to enter into contract changes up to and including twenty percent (20%) of the original contract price; and recognizing this ordinance as having an accelerated effective date.
Sponsors: Director of Public Works
Attachments: 1. Docket Memo 89061062 CS25011, 2. 89061062 31st St Connector Plan Phase1 CS25011

ORDINANCE NO. 250296

 

 

title

Sponsor: Director of Public Works Department

 

Authorizing the Director of Public Works to execute a design-build contract with Gunter Construction Company in the amount of $2,887,595.00 for the 31st St Connector Plan Phase 1 Sidewalks project, from Main Street to Gillham Plaza; authorizing the Director of Public Works to enter into contract changes up to and including twenty percent (20%) of the original contract price; and recognizing this ordinance as having an accelerated effective date.

 

body

WHEREAS, the Council approved Ordinance 241060, the fourth amendment to the Union Hill TIF agreement, estimating and appropriating $4,589,700.00 for Union Hill Streetscape improvements; NOW, THEREFORE,

 

           BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

 

Section 1.  That the Director of Public Works is hereby authorized to execute a design-build contract with Gunter Construction Company in the amount of $2,887,595.00 for the 31st St Connector Plan Phase 1 Sidewalks project, from Main Street to Forest Street from funds previously appropriated to account:

 

25-3090-895914-B-89061082                                                               31st Connector Plan Ph1 Sdwk                      $2,887,595.00

 

A copy of the contract is on file in the office of the Director of Public Works

 

Section 2.  Authorizing the Director of Public Works to enter into contract changes up to and including twenty percent (20%) of the original contract price.

 

Section 3. That this ordinance, relating to the design, repair, maintenance or construction of a public improvement, is recognized as an ordinance with an accelerated effective date as provided by Section 503(a)(3)(D) of the City Charter and shall take effect in accordance with Section 503, City Charter.

end

______________________________________________________

 

I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.

 

 

____________________

Tammy L. Queen

Director of Finance

 

 

Approved as to form:

 

 

______________________________

Dustin E. Johnson

Assistant City Attorney