[COMMITTEE SUBSTITUTE FOR]ORDINANCE NO. 260968
title
Sponsor: Director of Public Works Department
COMMITTEE SUBSTITUTE
Authorizing the Director of Public Works to execute Amendment No. 1 to the Design Professional Services Agreement with Burns & McDonnell Engineering Company, Inc. in the amount of $1,688,170.27 for a total contract amount of $2,087,896.45 for the Prospect Avenue Safety Improvements Project between approximately East Linwood Boulevard and Emanuel Cleaver II Boulevard; directing the City Manager to evaluate alternative project delivery strategies to address immediate needs and conditions and report back to Council in sixty (60) days; and recognizing this ordinance as having an accelerated effective date.
TRANSPORTATION COMMITTEE recommends “Advance and Do Pass as a Committee Substitute, Debate”.
body
WHEREAS, Council approved Ordinance No. 250198 accepting the U.S. Department of Transportation Safe Streets and Roads for All grant awarded to the City for the Prospect Avenue Safety Improvements Project, which estimated and appropriated the $10,000,000.00 grant award in the Capital Improvements Grant Fund and appropriated $2,500,000.00 in the Vision Zero program as required for the local grant match; and
WHEREAS, the City conducted an RFP process for selection of the Design Professional for the Prospect Avenue Safety Improvements Project; and
WHEREAS, the Director of Public Works previously executed a Design Professional Services Agreement with Burns & McDonnell Engineering Company, Inc. in the amount of $399,726.18 for the Prospect Avenue Safety Improvements Project; and
WHEREAS, Amendment No. 1 is needed to complete survey, environmental, preliminary and final design for the Prospect Avenue Safety Improvements Project, including limited construction phase procurement and construction administration services; NOW, THEREFORE,
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of the Public Works Depa...