Title: Authorizing an $8,829,618.38 construction contract with Enerfab Power & Industrial, Inc., for the Secondary Switchgear Improvements at the Water Treatment Plant project; authorizing a maximum expenditure of $9,712,618.38; and authorizing a $1,140,766.00 Design Professional Services Amendment No. 1 for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant for Contract No. 9489 with HDR Engineering, Inc., for a total contract amount of $2,571,616.00.
Attachments: 1. 210374 Fact Sheet, 2. 210374 Fiscal Note, 3. 210374 Docket Memo, 4. 210374Approved DPS RFM
ORDINANCE NO. 210374


title

Authorizing an $8,829,618.38 construction contract with Enerfab Power & Industrial, Inc., for the Secondary Switchgear Improvements at the Water Treatment Plant project; authorizing a maximum expenditure of $9,712,618.38; and authorizing a $1,140,766.00 Design Professional Services Amendment No. 1 for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant for Contract No. 9489 with HDR Engineering, Inc., for a total contract amount of $2,571,616.00.

body

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of the Water Services Department is authorized to execute Contract No. 9569 in the amount of $8,829,618.38 with Enerfab Power & Industrial, Inc., for the Secondary Switchgear Improvements at the Water Treatment Plant project, Project No. 80002134. A copy of the contract is on file in the office of Water Services.
Section 2. That the Director of the Water Services Department is authorized a maximum expenditure of $9,712,618.38 from Account No. AL-8077-807773-611060- 80002134, Water Treatment, to satisfy the cost of this contract.
Section 3. That the Director of the Water Services Department is authorized to execute a Design Professional Services Amendment No. 1 to Contract No. 9489 in the amount of $1,140,766.00, for a total contract amount of $2,571,616.00 with HDR Engineering, Inc., for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant project, Project No. 80002134. A copy of the amendment is on file in the office of Water Services.
Section 4. That the Director of the Water Services Department is authorized a maximum expenditure of $1,140,766.00 from Account No. AL-8077-807773-611040- 80002134, Water Treatment, to satisfy the cost of this amendment.
_____________________________________________
I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, an...