File #: 210548    Version: 1 Name:
Type: Ordinance Status: Passed
File created: 6/17/2021 In control: Council
On agenda: 6/24/2021 Final action: 7/1/2021
Title: Estimating and appropriating the revenues from North American Specialty Insurance Company ("Surety") in the amount of $98,717.00 and $251,828.00 for Surety Payment related to the Water Main Replacement in the Area of N. Chaumiere to N. Cleveland, N.E. Russell to N.E. 43rd Street Project ("Chaumiere Project") (Project No. 80001944) and Water Main Replacement in the Area of N.W. Waukomis Drive, N.W. Englewood Boulevard to N.W. 64th Street Project ("Waukomis Dr. Project") (Project No. 80001988), respectively.
Attachments: 1. Authenticated Ordinance 210548, 2. 210548 Fact Sheet, 3. 210548 Fiscal Note, 4. 210548 Approp. Admin, 5. TIO 6-30-21 KCW Presentation Ord 210548
ORDINANCE NO. 210548

title
Estimating and appropriating the revenues from North American Specialty Insurance Company ("Surety") in the amount of $98,717.00 and $251,828.00 for Surety Payment related to the Water Main Replacement in the Area of N. Chaumiere to N. Cleveland, N.E. Russell to N.E. 43rd Street Project ("Chaumiere Project") (Project No. 80001944) and Water Main Replacement in the Area of N.W. Waukomis Drive, N.W. Englewood Boulevard to N.W. 64th Street Project ("Waukomis Dr. Project") (Project No. 80001988), respectively.

body
WHEREAS, on February 9, 2021, Blue Nile Contractors Inc. signed a Voluntary Letter of Default issued to North American Specialty Insurance Company ("Surety"), in which Blue Nile Contractors, Inc., indicated that it was unable to perform the Contract, and thus it was in default of the Contract; and

WHEREAS, the City and Surety entered into a tender agreement whereby the City agreed to release Blue Nile Contractors, Inc., of its obligations; and

WHEREAS, Surety has tendered to City a completion contractor, Site Rite Construction Company ("Completing Contractor"); and

WHEREAS, the Surety will pay to City the sum of $98,717.00 and $251,828.00, representing the additional cost of performing the work with the Completing Contractors for the Chaumiere Project and Waukomis Drive Project; NOW THEREFORE,

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section 1. That the revenue in the following account of Fund No. 8077, the Water Revenue Bond Series 2020A Fund, is hereby estimated in the following amount:

AL-8077-800000-581160-80001944 Contr. in Aid of Construction $ 98,717.00

Section 2. That the sum of $98,717.00 is hereby appropriated from the Unappropriated Fund Balance of Fund 8077, the Water Revenue Bond Series 2020A Fund:

AL-8077-807705-611060-80001944 WMR Replacement Program $ 98,717.00

Section 3. That the revenue in the following account of Fund No. 8010, the Water Fund is hereby es...

Click here for full text