ORDINANCE NO. 240974
title
Sponsor: Director of Water Services Department
Authorizing a $7,724,800.00 construction contract with Infrastructure Solutions, LLC, for the Water Main Replacement along Prospect Avenue from E. Linwood Boulevard to E. 63rd Street (Phase II) project; and authorizing a maximum expenditure of $8,497,280.00.
body
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of the Water Services Department is authorized to execute Contract No. 9913 in the amount of $7,724,800.00 with Infrastructure Solutions, LLC, for the Water Main Replacement along Prospect Avenue from E. Linwood Boulevard to E. 63rd Street (Phase II) project, Project No. 80002274. A copy of the contract is on file in the office of Water Services.
Section 2. That the Director of Water Services is authorized to expend up to the sum of $8,497,280.00 from Account No. AL-8081-807705-611060-80002222, Water Main Replacement Program, to satisfy the cost of this contract.
end
______________________________________________________
I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.
______________________________
Tammy L. Queen
Director of Finance
Approved as to form:
______________________________
Mark P. Jones
Senior Associate City Attorney