ORDINANCE NO. 250571
title
Sponsor: Director of Water Services Department
Authorizing a $2,700,000.00 construction contract with Infrastructure Solutions, LLC, for the Emergency Water Distribution Repairs, Renewal No. 2 project; and recognizing this ordinance as having an accelerated effective date.
body
WHEREAS, City Council passed Ordinance No. 230959 on November 30, 2023, authorizing a $2,400,000.00 construction contract with Infrastructure Solutions, LLC, for the Emergency Water Distribution Repairs project and authorizing two successive renewal options with further City Council approval; and
WHEREAS, the City executed a no-cost Change Order No. 1 on August 20, 2024, changing permit requirements in the contract, and a $230,000.00 Change Order No. 2 on September 20, 2024, for work to continue before execution of Renewal No. 1 due to a high number of emergencies; and
WHEREAS, City Council passed Ordinance No. 240912 on October 24, 2024, authorizing a $2,700,000.00 construction contract with Infrastructure Solutions, LLC, for the Emergency Water Distribution Repairs, Renewal No. 1 project and authorizing one successive renewal option with further City Council approval; and
WHEREAS, this proposed $2,700,000.00 ordinance is for the final renewal option for the Emergency Water Distribution Repairs project; NOW, THEREFORE,
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of the Water Services Department is authorized to execute Contract No. 9829-2 in the amount of $2,700,000.00 with Infrastructure Solutions, LLC, for the Emergency Water Distribution Repairs, Renewal No. 2 project, Project No. 80002486. A copy of the contract is on file in the office of Water Services.
Section 2. That the Director of Water Services is authorized to expend up to the sum of $2,700,000.00 from Account No. 26-8010-802010-B, Division of Distribution - Pipeline, to satisfy the cost ...
Click here for full text