ORDINANCE NO. 250510
title
Sponsor: Director of Water Services Department
Authorizing a $2,054,790.00 design professional services contract Amendment No. 8 to Contract No. 1394 with Carollo Engineers, Inc., for the Blue River Wastewater Treatment Plant (WWTP) Biosolids Facility project for a total contract amount of $22,602,694.77; authorizing an extension of the term for an additional 504 days for a total term of 3,059 days (8.38 years); and recognizing this ordinance as having an accelerated effective date.
body
WHEREAS, the City Council passed Ordinance No. 180507 on July 19, 2018, authorizing a $6,327,902.77 design professional services contract, which was executed by the City on August 15, 2018, with Carollo Engineers, Inc., for the Blue River WWTP Biosolids Facility project; and
WHEREAS, the City executed a no-cost Amendment No. 1 on August 13, 2019, to redistribute funds within the contract; and
WHEREAS, the City Council passed Ordinance No. 190815 on October 10, 2019, authorizing a $2,220,000.00 design professional services contract Amendment No. 2, which was executed by the City on November 20, 2019, for scope of services changes to add procurement phase services to the project; and
WHEREAS, the City Council passed Ordinance No. 200954 on November 12, 2020, authorizing a $5,170,000.00 design professional services contract Amendment No. 3, which was executed by the City on January 6, 2021, for construction phase services for Year 1 of the project and an extension of the term by five (5) years for a total contract term of seven (7) years; and
WHEREAS, the City executed a $2,711,325.00 Amendment No. 4 on February 14, 2022, under funding approved in Ordinance No. 200954, for construction phase services, engineering services and optional services for Year 2 of the project; and
WHEREAS, the City executed a no-cost Amendment No. 5 on April 26, 2023, to redistribute funds within the contract; and
WHEREAS, the ...