ORDINANCE NO. 240039
title
Sponsor: Director of Water Services Department
Authorizing a $3,824,431.00 construction contract with Kissick Construction Company, Inc., for the Inflow and Infiltration (I/I) Reduction: Birmingham 3 project; authorizing a maximum expenditure of $4,207,000.00; authorizing a $560,000.00 design professional services Amendment No. 1 to Contract No. 1509 with Olsson Associates, Inc., for the I/I Reduction: Birmingham 3 project for a total contract amount of $1,310,000.00; and recognizing this ordinance as having an accelerated effective date.
body
WHEREAS, City Council passed Ordinance No. 190199 on March 21, 2019, authorizing a $750,000.00 design professional services Contract No. 1509 with Olsson Associates, Inc., for the I/I Reduction: Birmingham 3 project; and
WHEREAS, this proposed ordinance is for authorization of a construction project and design professional services Amendment No. 1 for the I/I Reduction: Birmingham 3 project; NOW, THEREFORE,
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of the Water Services Department is authorized to execute Contract No. 1528 in the amount of $3,824,431.00 with Kissick Construction Company, Inc., for the I/I Reduction: Birmingham 3 project, Project No. 81000834. A copy of the contract is on file in the office of Water Services.
Section 2. That the Director of Water Services Department is authorized to expend up to a maximum of $4,207,000.00 from Account No. AL-8193-807769-611060-81000834, Overflow Control Program, to satisfy the cost of this contract.
Section 3. That the Director of the Water Services Department is authorized to execute a Design Professional Services Amendment No. 1 to Contract No. 1509 in the amount of $560,000.00, for a total contract amount of $1,310,000.00, with Olsson Associates, Inc., for the I/I Reduction: Birmingham 3 project, Project No. 81000834. A copy of the contract is ...