ORDINANCE NO. 240312
title
Sponsor: Director of the Water Services Department
Authorizing a $10,270,001.72 construction contract with Mark One Electric Company, Inc., for the Wastewater SCADA System Improvements Phase 2 project; authorizing a maximum expenditure of $11,300,000.00; authorizing a $2,043,121.00 design professional services Amendment No. 3 to Contract No. 1443, for the Wastewater SCADA project with Black & Veatch Corporation, for a total contract amount of $6,731,108.00; authorizing an extension of the term of Contract No. 1443 for an additional 365 days for a total term of 3,823 days (approximately 10.47 years); and recognizing this ordinance as having an accelerated effective date.
body
WHEREAS, City Council approved Ordinance No. 180416 on June 7, 2018, authorizing a $1,370,672.00 design professional services contract with Black & Veatch Corporation for the Wastewater SCADA project; and
WHEREAS, City Council approved Ordinance No. 200622 on August 27, 2020, authorizing a $999,189.00 Amendment No. 1 to the design professional services Contract No. 1443 with Black & Veatch Corporation for the Wastewater SCADA project for engineering office and field representative construction phase services plus adding 8 years to the contract's term; and
WHEREAS, City Council approved Ordinance No. 211107 on January 16, 2022, authorizing a $2,318,126.00 Amendment No. 2 to the design professional services Contract No. 1443 with Black & Veatch Corporation for the expansion of the Phase 1 construction phase services and for the addition of Phase 2 design services of Wastewater SCADA implementation of remaining sites and further development of standards documents; and
WHEREAS, this proposed ordinance is for authorization of a construction project for the Wastewater SCADA System Improvements Phase 2 and design professional services construction phase services and a time extension to Amendment No. 3 for the Wastewater SCADA proje...