ORDINANCE NO. 250323
title
Sponsor: Director of Water Services Department
Authorizing a $949,936.00 design professional services contract Amendment No. 1 to Contract No. 9613 with Burns & McDonnell Engineering Company, Inc., for the Water Main Replacement - 16-Inch Redundant Feed to the Downtown Airport project for a total contract amount of $1,224,936.00; and recognizing this ordinance as having an accelerated effective date.
body
WHEREAS, the City executed a $275,000.00 design professional services contract with Burns & McDonnell Engineering Company, Inc., for the Water Main Replacement - 16" Redundant Feed to the Downtown Airport project on June 23, 2023; and
WHEREAS, this proposed ordinance is for a $949,936.00 Amendment No. 1 for an extension of approximately 5,000 linear feet of 16-inch diameter water main from Wyoming Street & W. 8th Street under the Missouri River to the Kansas City Airport - Wheeler Field (Downtown Airport), including approximately 3,300 LF installed via horizontal directional drill; NOW, THEREFORE,
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of Water Services Department is authorized to execute Amendment No. 1 to Contract No. 9613 in the amount of $949,936.00, for a total contract amount of $1,224,936.00 with Burns & McDonnell Engineering Company, Inc., for the Water Main Replacement - 16-Inch Redundant Feed to the Downtown Airport project, Project No. 80002269. A copy of this amendment is on file in the office of Water Services.
Section 2. That the Director of Water Services is authorized to expend up to the sum of $949,936.00 from Account No. 26-8010-807705-611040-80002269, Water Main Replacement Program, to satisfy the cost of this amendment.
Section 3. That this ordinance, relating to the design, repair, maintenance or construction of a public improvement, is recognized as an ordinance with an accelerated effective date as pr...
Click here for full text