Title: Sponsor: Director of Public Works Department Authorizing Amendment No. 3 to a design professional services agreement with WSP, Inc. in the amount of $695,794.23 for Grand Boulevard Bridge Bike/Pedestrian Accommodations project for a total contract amount of $1,797,249.16; and recognizing this ordinance as having an accelerated effective date.
Sponsors: Director of Public Works
Attachments: 1. Grand Ave Bike Ped Bridge Inspection Docket Memo, 2. Ordinance TMP-5600 Text File, 3. Ordinance 250602-Revised CUP Summary-89005595-A3, 4. PW TIO slides 072925
Related files: 220777, 200957
ORDINANCE NO. 250602


title
Sponsor: Director of Public Works Department

Authorizing Amendment No. 3 to a design professional services agreement with WSP, Inc. in the amount of $695,794.23 for Grand Boulevard Bridge Bike/Pedestrian Accommodations project for a total contract amount of $1,797,249.16; and recognizing this ordinance as having an accelerated effective date.

body
WHEREAS, Ordinance 200957 authorized the Director of Public Works to execute a contract with WSP USA, Inc for a contract amount of $701,888.70 for design services for the Grand Boulevard Bridge Bike/Pedestrian Accommodations project; and

WHEREAS, Ordinance 220777 authorized the Director of Public Works to execute Amendment No. 1 with WSP, Inc in the amount of $299,894.91 for a total amount of $1,001,783.61 for additional design services for the Grand Boulevard Bridge Bike/Pedestrian Accommodations project; and

WHEREAS, the Director of Public Works authorized Amendment No. 2 to a design professional services agreement with WSP USA, Inc. in the amount of $99,671.32 for a total contract amount of $1,101,454.93 for additional design study scope items; and

WHEREAS, Amendment No. 3 to a design professional services agreement with WSP USA, Inc.is needed for archaeologic monitoring, railroad coordination, construction inspection and monitoring, and field observation; NOW, THEREFORE,

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section 1. That the Director of Public Works is authorized to execute Amendment No. 3to a design professional contract with WSP, Inc. in the amount of $695,794.23, for a total contract amount of $1,797,249.16, from funds previously appropriated to account 26-3090-897086-B-89005595. A copy of the agreement is on file in the Public Works Department.

26-3090-897086-B-89005595 Grand Boulevard - 3rd Street to Riverfront $695,794.23

Section 2. That this ordinance, relating to the design, repair, maintenance or constr...