ORDINANCE NO. 250663
title
Sponsor: Director of Water Services Department
Authorizing a $110,000.00 design professional services contract Amendment No. 2 to Contract No. 9489 with HDR Engineering, Inc., for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant project for a total contract amount of $2,681,616.00; authorizing an extension of the term for an additional 761 days for a total term of 2,660 days (7.3 years); and recognizing this ordinance as having an accelerated effective date.
body
WHEREAS, City Council passed Ordinance No. 190333 on May 2, 2019, authorizing a $1,430,850.00 design professional services contract, which was executed by the City on July 23, 2019, with HDR Engineering, Inc., for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant project; and
WHEREAS, City Council passed Ordinance No. 210374 on May 6, 2021 authorizing a $1,140,766.00 design professional services contract Amendment No. 1, which was executed by the City on July 27, 2021, for construction phase services and resident phase services; and
WHEREAS, this proposed ordinance is for a $110,000.00 Amendment No. 2 for construction phase services for continuous construction of the 120 volt station power at the Secondary Pump Station, and an extension of the term for an additional 761 days for a total term of 2,660 days (7.3 years); NOW, THEREFORE,
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of the Water Services Department is authorized to execute Amendment No. 2 to Contract No. 9489 in the amount of $110,000.00, for a total contract amount of $2,681,616.00, with HDR Engineering, Inc., for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant project, Project No. 80002134. A copy of this amendment is on file in the office of Water Services.
Section 2. That the Director of Water Services is authorized a maximum expenditure of $110,000....