File #: 230702    Version: 1 Name:
Type: Ordinance Status: Passed
File created: 7/25/2023 In control: Council
On agenda: 8/24/2023 Final action: 8/24/2023
Title: Sponsor: Director of General Services Department Authorizing a $17,416,817.00 an agreement with McCownGordon Construction, LLC., for Phase 2 of Project No. 07P22025-02 - City Hall Garage and South Plaza Restoration CM@Risk for a total contract amount of $17,456,817.00; authorizing a 1% Arts contribution of $153,063.00 for Project No. 07P22025-02 - City Hall Garage and South Plaza Restoration CM@Risk for artwork to be constructed at the project site; and recognizing this ordinance as having an accelerated effective date.
Sponsors: Director of General Services
Attachments: 1. CREO 230702, 2. MBE WBE, 3. Docket Memo, 4. CREO, 5. MBE WBE, 6. Power Point 230702, 7. Contract Amendment 1, 8. Authenticated Ordinance 230702
ORDINANCE NO. 230702


title
Sponsor: Director of General Services Department

Authorizing a $17,416,817.00 an agreement with McCownGordon Construction, LLC., for Phase 2 of Project No. 07P22025-02 - City Hall Garage and South Plaza Restoration CM@Risk for a total contract amount of $17,456,817.00; authorizing a 1% Arts contribution of $153,063.00 for Project No. 07P22025-02 - City Hall Garage and South Plaza Restoration CM@Risk for artwork to be constructed at the project site; and recognizing this ordinance as having an accelerated effective date.

body
WHEREAS, Ordinance No. 230197 appropriated $21,000,000.00 to Account No. AL-3448-079712-B from Special Obligations Bonds Series 2023B for reconstruction and renovation of the City Hall Garage and South Plaza of the City Hall, Kansas City, Missouri; and

WHEREAS, McCownGordon Construction, LLC., (the "CM@Risk") is the successful bidder for Project No. 07P22025-02 - City Hall Garage and South Plaza Restoration CM@Risk (the "Project"); and

WHEREAS, the Project is comprised of an initial pre-construction services phase ("Phase 1") followed by an optional construction services phase ("Phase 2"); and

WHEREAS, the Director of General Services entered into a $40,000.00 contract with the CM@Risk for the Phase 1 pre-construction services work for the Project; and

WHEREAS, the Director of General Services and the CM@Risk have agreed on a Final Guaranteed Maximum Price (the "FGMP") in the amount of $17,416,817.00 for the Phase 2 construction services work for the Project;

WHEREAS, the 1% Arts contribution for the Project for artwork to be constructed for the project is in the amount of $153,063.00; NOW, THEREFORE,

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section 1. That the Director of General Services Department is hereby authorized to execute a contract in the amount of $17,416,817.00 with McCownGordon Construction, LLC., for Ph...

Click here for full text