File #: 230315    Version: Name:
Type: Ordinance Status: Passed
File created: 3/14/2023 In control: Council
On agenda: 5/25/2023 Final action:
Title: Sponsor: Director of Public Works Department Reducing an appropriation in the amount of $2,842,818.83 in the General Obligation Series 2018 and 2021 Q1 Bond Funds and appropriating $2,842,818.83 from the Unappropriated Fund Balance in the General Obligation Series 2018 and 2021 Q1 Bond Funds to the North Green Hills Road Reconstruction Project account; authorizing execution of a $16,072,885.85 contract with Pyramid Contractors, Inc. for the project; and recognizing this ordinance as having an accelerated effective date.
Sponsors: Director of Public Works
Attachments: 1. 230315 Docket Memo, 2. 230315 Signed_Goal Per City Code 210991_FICB_N-A_20211222172121_8880 (2), 3. Docket Memo 89008087 N Green Hills - Construction ver2, 4. Appropriation N Green Hills Rd construction ver2, 5. Ordinance 230315 Testimony, 6. Public Testimony - KCMO Letter - N. Green Hills Road 042423, 7. Ordinance 230315 AMY AMDY M Testimony, 8. Re_ Ordinance 230315 Testimony AMY, 9. Ordinance 230315 Testimony, 10. Colored Compared 230315, 11. Ordinance 230315-CUP Summary-89008087-Leavenworth, 12. 230315-CUP Summary-89008087-Leavenworth, 13. Public Testimony 230315-Lauren Kaaz, 14. Public Testimony 230315 - Greg D. Kaaz, 15. Ordinance 230315 Aaron Schmidt, 16. Ordinance 230315 - Sheli Blakemore, 17. Public Testimony Cards 230315, 18. Alternate-Ordinance 230315-CUP Summary-89008087-Pyramid, 19. Ordinance 230315-CUP Summary-89008087-Leavenworth, 20. Authenticated Ordinance 230315C.S, A.A., 21. Project Manual on File
Related files: 230304, 230313
committeesub
[SECOND COMMITTEE SUBSTITUTE FOR] ORDINANCE NO. 230315

title
Sponsor: Director of Public Works Department

Reducing an appropriation in the amount of $2,842,818.83 in the General Obligation Series 2018 and 2021 Q1 Bond Funds and appropriating $2,842,818.83 from the Unappropriated Fund Balance in the General Obligation Series 2018 and 2021 Q1 Bond Funds to the North Green Hills Road Reconstruction Project account; authorizing execution of a $16,072,885.85 contract with Pyramid Contractors, Inc. for the project; and recognizing this ordinance as having an accelerated effective date.

body
WHEREAS, North Green Hills Road was constructed in the 1940's as a rural two-lane road with eleven-foot lanes and narrow gravel shoulders, and as the area has urbanized this does not meet City standards for safe horizontal and vertical geometry and forces pedestrians who are accessing employment and transit service along North Barry Road to walk on the narrow gravel shoulders or in the street, and

WHEREAS, N.W. 68th Street reconstruction was recently completed under budget and funding is available to assist with completing the North Green Hills Road reconstruction and the proposed improvements are a two/three lane street reconstruction with sidewalks and a sidewalk trail, and will complete reconstruction of Green Hills Road between N.W. 68th Street and Barry Road as outlined in the 2006 N.W. Waukomis Drive/North Green Hills Improvement study; and
WHEREAS, bids were opened on January 10, 2023 and work will include the roadway reconstruction to current urban standards and replacement of the KCI Water Transmission Main; NOW, THEREFORE,
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section 1. That the sum of $2,842,818.83 is hereby reduced in the GO Bond 2021 and 2018 Q1 Funds:

AL-3521-898012-B-89008842 N.W. 68th Street Reconstruction $2,838,318.07
AL-3518-898012-B-89008842 N.W. 68th Street Reconstruction ...