Skip to main content
File #: 230317    Version: 1 Name:
Type: Ordinance Status: Passed
File created: 3/20/2023 In control: Council
On agenda: 5/4/2023 Final action: 5/4/2023
Title: Sponsor: Director of Public Works Department Reducing an appropriation in the amount of $8,000,000.00 in the Go Bond 2023 Q2 Fund; appropriating the amount from the Unappropriated Fund Balance in the Go Bond 2023 Q2 Fund to the Swope Park Industrial Flyover Bridge Project; authorizing a construction contract with Radmacher Brothers Excavating, Inc. in the amount of $7,946,504.44 for the Swope Park Industrial Flyover Bridge - Phase 2 Project; and recognizing this ordinance as having an accelerated effective date.
Sponsors: Director of Public Works
Attachments: 1. 230317 Docket Memo, 2. Docket Memo 89005580 Swope Park Flyover Bridge Construction, 3. Appropriation 89005580 Swope Bridge Construction, 4. 230317.Authenticated Ordinance, 5. Project Manual on File
Related files: 230318
ORDINANCE NO. 230317


title
Sponsor: Director of Public Works Department

Reducing an appropriation in the amount of $8,000,000.00 in the Go Bond 2023 Q2 Fund; appropriating the amount from the Unappropriated Fund Balance in the Go Bond 2023 Q2 Fund to the Swope Park Industrial Flyover Bridge Project; authorizing a construction contract with Radmacher Brothers Excavating, Inc. in the amount of $7,946,504.44 for the Swope Park Industrial Flyover Bridge - Phase 2 Project; and recognizing this ordinance as having an accelerated effective date.

body
WHEREAS, Council approved Ordinance No. 210047 authorizing the construction contract for the Swope Park Industrial Flyover Bridge - Phase 1 project; NOW, THEREFORE

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section 1. That the sum of $8,000,000.00 is hereby reduced in the following account of the Go Bond 2023 Q2 Fund:

AL-3623-808054-B-89005580 Swope Park Industrial Flyover $8,00,000.00

Section 2. That the amount of $8,000,000.00 is to be used for construction, inspection and Public Works staff costs is hereby appropriated from the Unappropriated Fund Balance in the Go Bond 2023 Q2 Fund to the following account:

AL-3623-898054-B-89005580 Swope Park Industrial Flyover $8,000,000.00

Section 3. That the Director of Public Works is hereby authorized to execute a $7,946,504.44 construction contract with Radmacher Brothers Excavating, Inc. for Project No. 89005580 Swope Park Industrial Flyover Bridge from GO Bond Flood Control Q2 funds previously appropriated to the following accounts:

AL-3321-898055-B-89005580 Swope Park Industrial Flyover Bridge $ 178,080.51
AL-3622-898055-B-89005580 Swope Park Industrial Flyover Bridge 1,081,297.52
AL-3623-898054-B-89005580 Swope Park Industrial Flyover Bridge 6,687,126.41
TOTAL: $7,946,504.44

A copy of the contract is on file in the office of the Director of Public Works.

...

Click here for full text



OLA LOGODo you need interpretation? We can help! OLA@kcmo.org 816-513-1030